ADDRAC Field Notes • Permits & planning

Before You Build: Residential Permits, Plans, Inspections, and Fees in Central Texas

Opens: Loading…

A practical guide for custom homes, remodels, additions, and ADU/casita projects across our eight service-area cities.

By ADDRAC Construction • October 10, 2026

← All field notes

Before you move a wall, add a bedroom, build a casita, or break ground on a custom home, there is one question worth answering: what approvals does this exact property and scope require?

The answer changes across Austin, Cedar Park, Leander, Georgetown, Liberty Hill, Dripping Springs, Lago Vista, and Jonestown. A permit application, a complete set of drawings, and the inspection schedule are related—but they are separate parts of getting a project built and closed out.

Start with the property, then the project.

A mailing address does not establish permitting jurisdiction. Verify city limits, extraterritorial jurisdiction (ETJ), county, floodplain, wastewater authority, and utility provider. An ETJ property may have a different approval path from a city-limit property. HOA or deed-restriction approval is a separate review and does not replace agency approval.

For an ADU/casita, confirm whether a second dwelling is allowed on the parcel before finalizing plans. Setbacks, lot coverage, access, parking, utility capacity, septic capacity, and applicable private restrictions can affect feasibility. A shed or accessory-building permit is not permission to create a dwelling.

What changes with the job scope?

Use this table to plan the initial conversation with the permitting authority. Local exemptions and the issued permit control the final requirements.

ProjectLikely approval pathDocuments and inspection focus
Paint, flooring, cabinet replacement with no structural or trade changesMay fall within local cosmetic-work exemptions; verify the complete scope.A small cosmetic project may not need a full architectural set. Moving wiring, pipes, walls, or equipment changes the question.
Kitchen/bath remodel with plumbing, electrical or HVAC changesApplicable building/remodel and trade permits; some cities offer limited-scope routes.Existing/proposed layout, fixture and equipment locations, affected circuits or piping; rough and final trade inspections as assigned.
Remove a load-bearing wall; enlarge structural openingsStructural remodel approval and applicable trades.Demolition and framing details, beam/header sizing, posts and load path to the foundation; engineering when required. Inspect before concealment.
Room addition or second-story additionAddition review, building and trade permits; site constraints also reviewed.Site plan, existing/proposed floor plans, foundation, roof and framing tie-ins, elevations, energy documents, MEP changes; foundation through final inspections.
Garage conversion to living space or an ADUConversion/remodel or small-project route determined by city; dwelling use must be approved.Egress, ceiling heights, fire separation, slab/moisture details, insulation, HVAC, electrical and plumbing; scope-specific inspections.
Detached ADU/casita or new custom homeNew dwelling review, building/trade approvals, plus applicable site and utility approvals.Full construction set, structural and energy documents, HVAC calculations, water/wastewater plan; phased inspections and occupancy closeout.

Scope examples are synthesized from Austin’s project categories and Cedar Park’s remodel/addition checklist.[1][5]

Architectural plans, engineering, MEPs, and shop drawings

A rendering shows the idea. Permit drawings explain what will be built, where it will sit, and how it complies. An “architectural plan set” does not automatically mean every sheet requires an architect’s seal. Required professional licenses, signatures, and seals depend on the project, applicable law, and the authority’s requirements.

DocumentWhat it coversWhen to expect it
Site / plot plan and surveyProperty lines, setbacks, easements, existing/proposed footprints, driveway, drainage, trees and utility locations.New homes, detached dwellings and footprint additions; civil/drainage engineering where site conditions or agency review require it.
Architectural / building drawingsDimensioned floor plans, elevations, sections, roof geometry, openings, life-safety features and assembly details.Complete set for new dwellings; affected areas and existing/proposed conditions for remodels.
Structural / engineered drawingsFoundation and reinforcement, framing, beams and connections, lateral bracing, and support of existing structure.New foundations and structural changes. Requirements vary: Leander’s new-home packet expressly calls for stamped foundation and wind-bracing plans.
MEP drawings and calculationsMechanical, electrical and plumbing layouts; service/panel loads, piping, ventilation and equipment information.Drawings match the affected trades. Formal engineered MEP sheets are not automatically required for every small replacement job.
HVAC Manual J, S and D; energy complianceJ calculates heating/cooling loads; S supports equipment selection; D addresses duct design. Energy documents describe code compliance.New HVAC and conditioned-space changes as required. Leander and Jonestown specifically request J/S/D in residential packets.
Shop / manufacturer drawingsFabrication and installation details for engineered trusses, steel, specialty framing, stairs/railings and other specified components.When the design, product, or reviewer requires them. Truss layouts/designs and specialty structural submittals need coordination with the overall building design.
Septic, floodplain, civil and supporting documentsWastewater design/capacity, elevation and flood documentation, grading/drainage or other site approvals.When the property or scope triggers them; adding a dwelling or plumbing can require reassessment of an existing septic system.

Shop drawings supplement the permit set. Obtain required design-professional review and agency acceptance before fabrication or installation. A deferred submittal needs the authority’s agreement; it is not a way to skip approval. Even cabinet shop drawings can be useful for construction coordination without being a routine municipal permit requirement.[4][7][10][20]

Additions need an actual tie-in design.

Show how new loads reach the foundation, how the old and new roofs shed water, how flashing and waterproofing connect, and how utilities and HVAC serve the added space. An existing-home drawing with a box labeled “addition” leaves too many construction questions unanswered.

The inspection stages to plan before construction

The assigned inspection list varies by scope. New homes and additions commonly involve the stages below; a minor trade project may require only a few. Schedule approvals before the work is buried or covered, and keep approved plans and required reports available.

Stage / hold pointWhat may need approval before proceeding
Site preparation and underground workRequired erosion/tree measures, layout, underground plumbing and utilities before backfill or concrete.
Foundation before the pourForms, reinforcement, beams/footings, embedded items and under-slab work. Upload required engineer letters; an engineer’s visit does not automatically replace the city inspection.
Structure and weather enclosureFraming, connections, bracing, roof/wall sheathing and flashing at the prescribed stage. Some jurisdictions require sheathing inspection before housewrap.
Rough mechanical, electrical and plumbingWiring, piping, ducts, required pressure tests, fire blocking and other concealed work before insulation or wall finishes.
Insulation and wallboardInsulation/air sealing and, where assigned, wallboard fastening before taping or finishing.
Final approvals and occupancyBuilding and trade finals, safety devices, energy/duct/air-leakage reports when required, site closeout and utility releases. Obtain the jurisdiction’s occupancy authorization before using a new dwelling.

Inspection guidance: Austin checklists; Leander’s published sequence (an older guide, so use the current permit list for actual scheduling); Jonestown’s June 2026 packet.[2][9][20]

City requirements and agency fees

How to read the fees: SF means square feet, but the area being billed differs by city. Fees below are selected residential items, not an all-inclusive project total. Add only the charges assigned to your scope. Plan preparation, engineering, surveys, testing and contractor permit coordination are private services outside these agency fees.

Research date: October 10, 2026. Source dates are identified below. Confirm the current adopted schedule, area calculation, inspection inclusions and utility/impact charges when the application is classified. Review notes flag rates that need further agency confirmation.

Austin

Use Residential Plan Review for new homes, additions and ADUs; interior remodels, garage conversions and eligible express work have separate routes. New construction requires foundation, framing and wind-bracing information. The reviewer may accept a structural verification report for qualifying remodel/conversion work. Complete building/trade approvals and assigned inspections before occupancy.[1][2]

Fees below are from the schedule effective October 1, 2026. Review charges and building/trade permit charges are separate.[3]

Permit and inspection fees

Permit or inspection itemPublished agency fee / basis
Application processing / express plan review$112.76 each listed category
New-construction review$986.15 base; larger-area tiers apply. The 2,001–3,000 SF row is $1,380.61 + $0.1972/SF over 2,000.
Addition/remodel review$197.23 base; tiered increases. Above 500 SF: $1,048.12 + $0.1634/SF over 500.
Small-project review, including qualifying garage conversions$146.15
Building / electrical / mechanical / plumbing / energy permit bases$318.48 / $183.69 / $127.68 / $220.47 / $72.38; larger-area formulas apply separately.
Inspections and reinspectionsPermit fees include one inspection per required type; applicable reinspection $83.85. Express/kitchen inspection $72.96; after-hours $166.57/hour, one-hour minimum.

Tree, floodplain, drainage, fire/WUI and utility reviews may add charges. Request the project’s itemized assessment.

Cedar Park

New residential submittals include plot, architectural, foundation, framing/roof or truss, MEP and energy documentation. Addition plans must show footing/beam details, the connection to existing framing, and changed elevations; remodels show before/after layouts. Obtain assigned rough and final inspections before covering work.[4][5]

Selected fees from the codified schedule:[6]

Permit and inspection fees

Permit or inspection itemPublished agency fee / basis
New single-family / townhouse building permit$0.10/SF, $25 minimum; total foundation/floor area includes porches and patios.
New-home plan review$50
New-home plumbing and electrical$0.10/SF each, $25 minimum each
New-home mechanical$100 per living unit + $25 per floor above the first
Residential remodelBuilding $50; review $100; plumbing, electrical and mechanical $100 each when applicable. Confirm addition classification.
Reinspection$75
Floodplain development / LOMR-CLOMR review$500 each applicable category

Leander

Submit new-home documents through the Development Hub: architectural/framing plans, stamped foundation and wind-bracing plans, energy compliance, HVAC calculations and applicable septic approval. The packet also addresses engineered structural sheets for homes over 5,000 SF. For an addition on septic, demonstrate capacity for the added use. Inspections become available after issuance and fee payment; coordinate the assigned building/trade finals.[7]

Fee sheet updated October 2, 2025:[8]

Permit and inspection fees

Permit or inspection itemPublished agency fee / basis
New-home application / review$200 application. Under 3,000 SF: $50 review without master plan, $20 with master plan; over 3,000 SF: $0.05/SF. Confirm the 3,000-SF boundary.
New-home building and trades$0.15/SF each for building, plumbing, mechanical and electrical; $40 minimum each.
Remodel, addition or other habitable-space application / review$50 application + $50 review
Remodel/addition building and applicable trades$0.05/SF of calculated work area per category; $40 minimum each. Temporary/permanent power may be additional.
Technology / additional review$25 where application cost ≤$250; $40 above $250. $50 resubmittal after third review.
Reinspection$100 each

Georgetown

The new-residential path covers houses, ADUs and additions. The checklist calls for a plot plan, architectural and MEP information, stamped engineered foundation, energy documents and framing/bracing information as applicable. Historic properties may need a Certificate of Appropriateness. Georgetown does not issue a separate residential Certificate of Occupancy: the approved building final serves that purpose.[10]

Confirm the current fee assessment.

The city links a construction fee schedule revised June 12, 2026, but that PDF could not be retrieved. The historical October 2025 city record below provides context only; it is not a verified current quote. Ask Building Inspections to confirm the new/addition formula and what is bundled.[11][12]

Permit and inspection fees

Permit or inspection itemPublished agency fee / basis
New-home fee components — historical October 2025 recordApplication $125; permit row $125 + $0.50/SF; technology $25. Confirm the current formula, billed area and bundled trades before budgeting.
Remodel/addition — historical recordApplication $60; a separate $60 + $0.50/SF row; technology $10. Confirm how the city applies the rows; do not assume a current total.
Individual trades — historical record$50 permit + $10 technology each; ground-up trades listed as included with validation.
Residential reinspections — historical record$50 first / $100 second / $150 third; confirm against June 2026 schedule.

Liberty Hill

The city requires permits for new construction and many physical, structural or MEP changes, while identifying certain cosmetic exemptions. Submit plans electronically through MyPermitNow/MGO. Match architectural, foundation/framing and trade details to scope, then follow the issued inspection list. Inspection requests before 3 p.m. are scheduled for the next business day under the posted process.[13]

Codified fee schedule, amended May 2026:[14]

Permit and inspection fees

Permit or inspection itemPublished agency fee / basis
Residential application / plan review$100 application; review $100 up to 5,000 SF. Higher-area tier applies above that threshold.
New one-/two-family dwelling, up to 5,000 SF$1,250, listed as including all permits; application/review/technology shown separately.
Remodel, repair, alteration or addition$50 + $50 per MEP trade, maximum $200 for this permit category.
Technology$15 added to all permits
Residential reinspections$65 first / $130 second / $195 third
Other required inspections / utility releaseSchedule also lists $65 for required inspections/reinspections and $50 meter/permanent-power release. Confirm package inclusions and which row governs each visit.

Dripping Springs

Start with a jurisdiction/scope check: city-limit work and ETJ subdivisions covered by development agreements can have different obligations. Apply digitally through MGO. Confirm architectural/site, structural, MEP, energy, landscape and lighting submittals for the address. Follow assigned inspections and obtain occupancy authorization for a new dwelling.[15]

The city’s approved-change notice establishes the January 2026 formulas below. Other inspection figures come from its approved FY2025–26 schedule; reconfirm those against FY2027 when budgeting.[16][17]

Permit and inspection fees

Permit or inspection itemPublished agency fee / basis
New house or additional dwelling$1.00/SF of conditioned space; includes processing, plan reviews and required inspections. Reinspections extra.
Addition, alteration, remodel or accessory structure$0.50/SF of total project area; processing/review included, scope-specific inspections additional.
Inspection not covered by residential permit — FY2026 reference$100 each
Reinspection / after-hours — FY2026 reference$150 / $200
Standalone trade — FY2026 reference$200 + inspections for scope
Residential OSSF — FY2026 reference$600 per system; confirm city wastewater jurisdiction and current rate.

Earlier budget documents show different SF rates; use the later approved-change notice for the January 2026 formulas and obtain the current itemized assessment.

Lago Vista

New construction and major remodel applications use the city’s online permit system; contractor registration is part of the process. Confirm residential/ADU zoning eligibility, required plan review, engineered foundation/framing submittals and the assigned inspection list before work starts.[18]

Selected adopted May 21, 2026 fees:[19]

Permit and inspection fees

Permit or inspection itemPublished agency fee / basis
New single-family residence$400 review + $0.50/SF
New single-family residence in floodplain$500 review + $0.50/SF
Remodel without additions$100
Additions / remodel with additionsSchedule has an “Additions” row at $200 and a “Remodel with additions” row printed as “$600.00; $0.20.” Obtain classification and the latter formula’s units; these are not automatically additive.
Inspections / reinspectionsGeneral inspection $100; first reinspection $150, second $300, third+ $500. Confirm which inspections are included in the permit and which are billed.
After-hours / weekend-holiday / third-party inspection$300 / $350 / 115% of cost
File creation / utility extension estimate$100 / $250; confirm applicability

Jonestown

The June 2026 packet requests residential plans, energy compliance and signed Manual J/S/D. Where septic applies, coordinate LCRA authorization. The inspection sequence includes engineer foundation documentation before city pre-pour, sheathing before housewrap, framing/MEP before insulation, and wallboard before taping. Follow the issued checklist and obtain final/occupancy approval.[20]

Fee schedule revised July 9, 2026:[21]

Permit and inspection fees

Permit or inspection itemPublished agency fee / basis
New-home plan review$200
New-home building$0.20/SF at ≤2,500 SF; $0.25/SF above 2,500 SF. Building area includes porches and patios.
New-home plumbing, electrical, mechanicalEach $0.20/SF at ≤2,500 SF or $0.25/SF above; $55 minimum each. Mechanical is conditioned space only.
Remodel/addition review and building$150 review; building $55 at ≤275 SF, $0.25/SF above 275 SF.
Remodel/addition applicable tradesEach $55 at ≤275 SF or $0.25/SF above 275 SF.
Residential occupancy / technology$100 occupancy; $15 technology per permit
Repeat failed/not-ready inspection$100 first / $200 second / $300 third for the same inspection; same-day building-final reinspection adds $200.

County, septic, and LCRA approvals: separate from the city permit

A city building permit does not establish wastewater capacity or authorize every site improvement. Confirm the correct OSSF authority for the parcel. Do not add city, county and LCRA septic permit charges together unless each authority confirms that separate charges apply.

Travis County

The January 2026 development schedule lists these wastewater and inspection items. Development, drainage or floodplain review may be separate and address-specific.[22]

Permit or inspection itemPublished agency fee / basis
Private sewage permit, up to 500 gallons/day$712 + $10 state fee
Engineered construction OSSF permit, up to 500 gallons/day$1,262 + $10 state fee
Over 500 gallons/dayAdditional $125 per 500 gallons/day over 500, in the listed categories
Septic verification / non-permit OSSF inspection$92 per submission / $107 per inspection
Development multiphase/reinspection items$200 per inspection; schedule identifies reinspection after the initial free inspection. Confirm applicability to the development permit.

Williamson County

For properties served by its OSSF program, the county’s currently posted sheet, updated September 2025, lists:[23]

Permit or inspection itemPublished agency fee / basis
Residential conventional OSSF$510
Residential nonconventional / nonaerobic$610
Residential aerobic with routine maintenance$710
Extra site visit / extra inspection$100
New or additional design review$150

Hays County

County residential development requires a compliant parcel and applicable development/wastewater approvals. Check whether city review or an interlocal arrangement also applies. January 2026 county fees include:[25][24]

Permit or inspection itemPublished agency fee / basis
Development outside special flood hazard area$100, Class A
Development inside special flood hazard area$300, Class B habitable / Class C other development
Single-family OSSF application$610; schedule separately lists a $10 state fee on OSSF applications—confirm the assessed total.
Minor / major OSSF alteration$310 / $510, with the separately listed state fee
OSSF reinspection / tie-in inspection or design resubmission$150 each listed category

LCRA: Lake Travis and Highland Lakes wastewater jurisdiction

LCRA administers OSSF approvals within its designated lakeside jurisdiction; use the official map for the actual property. Building approval does not replace septic authorization. Posted fees include:[26][27]

Permit or inspection itemPublished agency fee / basis
Conventional OSSF$260 + $10 required state fee = $270
Professionally designed single-family OSSF$410 + $10 state fee = $420
Single-family facility reinspection$150; this covers the listed continued-use situations and is not a city building reinspection.
Extra site trip / permit revision / permit renewal$70 / $50 / $50

What else belongs in the permitting budget?

Ask for separate lines for agency charges, plan preparation, engineering, surveys, energy testing and permit coordination. Water/sewer impact fees, meters, tap fees, utility service changes, driveway/right-of-way approvals, tree work, floodplain review, replats or variances may add cost when triggered. They are not universal charges on every remodel.

A bedroom addition or casita can affect septic capacity even when the existing system is working well. A structural wall removal can require a beam design and foundation verification without increasing the home’s footprint. A straightforward finish update can have a much smaller approval package. Scope determines the path.

A smoother path from concept to final approval

  1. Confirm the address and use. Identify authorities, zoning, private restrictions, utilities and ADU eligibility.
  2. Define the work. Record demolition, structural changes, conditioned area and every affected trade.
  3. Build the right plan package. Coordinate architectural, structural, site, energy, MEP and manufacturer documents.
  4. Resolve review comments and obtain issuance. A submitted application is not a permit to begin construction.
  5. Plan inspection hold points. Keep work accessible and upload required engineering/testing reports.
  6. Close the permits. Complete corrections, final inspections, utility releases and required occupancy authorization.

Bring us the project. We’ll help define the path.

Planning a remodel, addition, ADU/casita, or custom home in Central Texas? Contact ADDRAC Construction with your property address, plans or ideas, and intended scope. We can review the construction needs, identify permitting questions, and prepare an estimate around the complete project.

Request a project estimate ↗

Visit ADDRAC Construction · Austin • Cedar Park • Leander • Georgetown • Liberty Hill • Dripping Springs • Lago Vista • Jonestown

This is a planning guide, not an agency approval or a guaranteed permit quote. Jurisdiction, adopted rules, billed area and the issued permit determine the requirements for a particular property. Confirm flagged rates with the permitting authority before setting your project budget.

Official sources and fee schedules

Reviewed October 10, 2026. Historical references and unresolved current-rate checks are identified in the corresponding city sections.

  1. Austin: Residential Plan Review
  2. Austin: Building Inspections and residential checklists
  3. Austin: FY 2026–27 residential fees, effective October 1, 2026
  4. Cedar Park: Residential Building Permit Guidelines, November 2025
  5. Cedar Park: Residential Remodel / Addition Submittal Checklist
  6. Cedar Park: Codified development service fees
  7. Leander: Residential Application Submittal Packet, July 2025
  8. Leander: Building Department Fees, October 2, 2025
  9. Leander: Residential Building Inspection Guidelines (2020; sequence reference)
  10. Georgetown: New Residential Construction, additions and ADUs
  11. Georgetown: Current building permit and inspection fee schedules landing page
  12. Georgetown: Comprehensive Fee Schedule, October 2025 record; historical reference
  13. Liberty Hill: Building Permits & Inspections
  14. Liberty Hill: Codified building permit and inspection fees, amended May 2026
  15. Dripping Springs: Building Department and jurisdiction guidance
  16. Dripping Springs: Approved residential fee change, effective January 1, 2026
  17. Dripping Springs: Approved FY 2025–26 fee schedule, residential inspection rows (historical reference)
  18. Lago Vista: Permitting
  19. Lago Vista: Adopted fee schedule, May 21, 2026, Ordinance 26-05-21-01
  20. Jonestown: Residential Building Packet, revised June 30, 2026
  21. Jonestown: City fee schedule, revised July 9, 2026
  22. Travis County: Development-related fees, effective January 2026
  23. Williamson County: OSSF fees, updated September 12, 2025